4. Environmental Impact Assessment Report

Environmental Impact Assessment Directive Flow Schematics (25 work days)

 

  • Preparation of the project presentation file
  • Submitting the project presentation file to the Ministry and the Ministry checks the file for compliance (5 work days)
  • Evaluation of the project presentation file (15 work days)
  • Ministerial decision stage (5 work days)
EIA required
EIA not required

Environmental Impact Assessment Procedure (38 work days)
 
  • Preparation and submitting of the project presentation file to the Ministry
  • Evaluation of the project presentation file by the Ministry and forming of an Analysis and Evaluation Commission (AEC)
  • Public participation and formatting (12 work days)
  • Submitting the EIA report to the Ministry (within 1 year at most)
  • The Ministry checks the file for compliance with the format (3 work days)
  • Analysis and evaluation by the Commission members (10 work days)
  • Final EIA report is submitted to the Ministry (5 work days)
  • Ministerial decision stage - EIA positive /EIA negative (5 work days)
Commencement of the investment in a maximum of five (5) years.
Cancellation of the investment